Draft preset · manifest.timeline
Critical path
First irreversible deadline in 2 days (2026-07-07 → 2026-08-23).
Commit campmates for Reno Hexayurt OSS
2026-07-07 → 2026-07-09 · slack 1d
Book Reno Hexayurt OSS · critical
2026-07-09 → 2026-07-09 · slack 0d
Confirm Reno Hexayurt OSS delivery
2026-07-10 → 2026-08-22 · slack 43d
Order Used ShiftPod 2
2026-07-07 → 2026-07-21 · slack 14d
Receive Used ShiftPod 2
2026-07-08 → 2026-08-22 · slack 25d
Order New ShiftPod 2
2026-07-07 → 2026-08-08 · slack 32d
Receive New ShiftPod 2
2026-07-08 → 2026-08-22 · slack 36d
Order Evaporative cooler
2026-07-07 → 2026-07-29 · slack 22d
Receive Evaporative cooler
2026-07-08 → 2026-08-22 · slack 36d
Order Honda EU2200i
2026-07-07 → 2026-07-29 · slack 22d
Receive Honda EU2200i
2026-07-08 → 2026-08-22 · slack 36d
Order Water containers
2026-07-07 → 2026-08-03 · slack 27d
Receive Water containers
2026-07-08 → 2026-08-22 · slack 39d
Order CO alarm
2026-07-07 → 2026-07-19 · slack 12d
Receive CO alarm
2026-07-08 → 2026-08-22 · slack 41d
Weigh everything that goes on the vehicle
2026-07-29 → 2026-08-22 · slack 24d
Finalize the load plan with measured weights
2026-07-30 → 2026-08-22 · slack 23d
Verify hatch clearance loaded
2026-07-31 → 2026-08-22 · slack 22d
Test-run the generator
2026-07-18 → 2026-08-22 · slack 35d