Draft preset · manifest.timeline

Critical path

First irreversible deadline in 2 days (2026-07-07 2026-08-23).

  1. Commit campmates for Reno Hexayurt OSS

    2026-07-072026-07-09 · slack 1d

  2. Book Reno Hexayurt OSS · critical

    2026-07-092026-07-09 · slack 0d

  3. Confirm Reno Hexayurt OSS delivery

    2026-07-102026-08-22 · slack 43d

  4. Order Used ShiftPod 2

    2026-07-072026-07-21 · slack 14d

  5. Receive Used ShiftPod 2

    2026-07-082026-08-22 · slack 25d

  6. Order New ShiftPod 2

    2026-07-072026-08-08 · slack 32d

  7. Receive New ShiftPod 2

    2026-07-082026-08-22 · slack 36d

  8. Order Evaporative cooler

    2026-07-072026-07-29 · slack 22d

  9. Receive Evaporative cooler

    2026-07-082026-08-22 · slack 36d

  10. Order Honda EU2200i

    2026-07-072026-07-29 · slack 22d

  11. Receive Honda EU2200i

    2026-07-082026-08-22 · slack 36d

  12. Order Water containers

    2026-07-072026-08-03 · slack 27d

  13. Receive Water containers

    2026-07-082026-08-22 · slack 39d

  14. Order CO alarm

    2026-07-072026-07-19 · slack 12d

  15. Receive CO alarm

    2026-07-082026-08-22 · slack 41d

  16. Weigh everything that goes on the vehicle

    2026-07-292026-08-22 · slack 24d

  17. Finalize the load plan with measured weights

    2026-07-302026-08-22 · slack 23d

  18. Verify hatch clearance loaded

    2026-07-312026-08-22 · slack 22d

  19. Test-run the generator

    2026-07-182026-08-22 · slack 35d